NSC construction progress as of December 20, 2017

Select another date

Within the NSC Project at the construction site the following works are being performed:

 

- Erection of Arch steelwork:

* Installation of the sealing anker beams on the roofs of Block V;
* Installation of the membrane on the roof of Block V.

- Technological building and auxiliary facilities:

* Installation of the following main systems:
   • Power supply system;
   • Ventilation, gas purification and conditioning;
   • Fire safety system;
   • Water supply and sewerage system;
   • Communication and industrial TV system;
   • Physical protection and access control system;
   • Integrated management and control system;
   • System of internal and transport connection;
   • Radiation monitoring system
* Work on grinding, pre-coating, coating, pouring, painting of floors, walls and ceilings inside the TB an FBAL is underway.

- Fire extinguishing pump station building with tanks:

* Electrical fitting works are in progress. Installation of a system of exhaust gases from diesel-driven pumps;

- Works on arranging the NSC internal and external space:

* Pipelines installation;
* Weather station establishment.

Other activity:

* Dismantling of the Turbine Hall light roof.

 

Nearest Events

On May, 15, 1976 according to the Preliminary Design requirement and SES the permanent radiation control in areas adjacent to the Chornobyl nuclear power plant was established
On May, 16, 1975 Commission on preparation and commissioning of ChNPP’s Unit 1 was established by Decree of ChNPP Director

News distribution