ISF-2 construction progress as of Fabruary 02, 2018

Select another date

Within the project the following activity was performed at the construction site:

- The work electrical part of the crane SWP-CR-04 was resumed;
- Reconfiguration of fire protection valves of the ventilation system;
- Adjusting the gaps and scalding (welding) of the sleeves of the penetrations of process pipelines;
- Fire retardant sealing of penetrations of process pipelines;
- Modification (sealing) of IAEA passages;
- Calibration of the crane load cells CR-08 room 305;
- Completed work on timber load monitoring LD-04 room 119;
- Manufacture of cable support models for organizing (ordering) cable routes BNG;
- Soldering cable penetrations (outside) BNG;
- Completed drilling holes and tapping in the door of CSM;
- Completing of executive & acceptance documentation according to the Contract;
- The development of test programs of technological components and systems;
- Preparation of Employer’s personnel training programmers;
- Commissioning on main technological equipment and auxiliary;
- Individual (Autonomous) tests of the System for technological process monitoring and controlling at the — systems for fuel canisters, double-wall shielded canisters handling and solid radioactive waste management;
- Inspection of the representative of the manufacturer of parallel manipulators, removal of comments on the results of inspection;
- Preparation of simulator for SFA capture;
- Completed elimination of remarks and re-testing of the TD-05/06 trolley in room 119;
- Completed elimination of remarks and re-testing of the double cover system TP;
- Elimination of remarks on the Cutting Machine;
- The preliminary checks of the Sliding Holder will continue — the calibration of the load cell;
- Commissioning works on double cover system for 200 l drums — checked in manual and manual mode;
- Elimination of remarks on the video surveillance system;
- Elimination of comments on the results of the first phase of the trial operation of the PPS; Phase 2 started of the trial operation of PPS
- Completion of comments on the SFP-CR-304 crane, testing of the Gostrud.

The Project General Contractor is Holtec. Works on the site are performed by the involved by Holtec subcontractors: CPI, UTEM, UTB, ZEM, EPI, BEM, “Kranservice”, “Conditioner”. In total 143 people were involved, as well as 1 units of transporting equipment.

 

Nearest Events

On May, 15, 1976 according to the Preliminary Design requirement and SES the permanent radiation control in areas adjacent to the Chornobyl nuclear power plant was established
On May, 16, 1975 Commission on preparation and commissioning of ChNPP’s Unit 1 was established by Decree of ChNPP Director

News distribution