ISF-2 construction progress as of Fabruary 07, 2018

Select another date

Within the project the following activity was performed at the construction site:

- Reconfiguration of fire protection valves of the ventilation system;
- Fire retardant sealing of penetrations of process pipelines;
- Calibration of the load cells and adjustment of crane positioning CR-07 and CR-08 room 305;
- Replacement of bolts on crane coupling CR-01;
- Manufacture of cable support models for organizing (ordering) cable routes BNG;
- Soldering cable penetrations (outside) BNG;
- Repairs and preventive works of SMTP — oil change is completed, leaks are eliminated;
- Measurements of holes in concrete structures (Completed on 24 modules) CSM;
- Elimination of comments on rainwater wells — concreting of covers
- Completing of executive & acceptance documentation according to the Contract;
- The development of test programs of technological components and systems;
- Preparation of Employer’s personnel training programmers;
- Commissioning on main technological equipment and auxiliary;
- Individual (Autonomous) tests of the System for technological process monitoring and controlling at the — systems for fuel canisters, double-wall shielded canisters handling and solid radioactive waste management;
- The preliminary checks of the Sliding Holder will continue;
- Commissioning works on double cover system for 200 l drums - checked in manual and automatic mode;
- Elimination of remarks on the video surveillance system;
- Preliminary checks of Luke protective SWP-CG-02 in pom. IS 102C6;
- Preliminary tests of LRW valves;
- Elimination of comments on the results of the first phase of the trial operation of the PPS; Phase 2 started of the trial operation of PPS.

The Project General Contractor is Holtec. Works on the site are performed by the involved by Holtec subcontractors: CPI, UTEM, UTB, ZEM, EPI, BEM, “Kranservice”, “Conditioner”. In total 126 people were involved, as well as 1 units of transporting equipment.

 

Nearest Events

On May, 15, 1976 according to the Preliminary Design requirement and SES the permanent radiation control in areas adjacent to the Chornobyl nuclear power plant was established
On May, 16, 1975 Commission on preparation and commissioning of ChNPP’s Unit 1 was established by Decree of ChNPP Director

News distribution