Support to Radioactive Waste Management in Ukraine

The project is financed from the funds of the European Union in the framework of the Programme “Instrument for Nuclear Safety Cooperation 2011. Part II”.

The Project general objective:

The Project objective is to improve safety and economic efficiency during management of all types of radioactive waste in Ukraine and, particularly, orientation of all kinds of works to minimize waste generation. Besides that, there is a long-term goal, i.e. continuous and safe disposal.

The Project objectives are as follows:

1. Optimization of the national infrastructure (transportation flow chart of radioactive waste management)
2. Investigation of radioactive waste burial and temporary storage sites in the Chornobyl exclusion zone
3. Comprehensive safety assessment of radioactive waste management facilities in the Chornobyl exclusion zone

The SSE ChNPP is the Recipient under Project U4.01/10C: the Optimization of the national transportation and handling infrastructure for radioactive waste management. The Project objective is to enhance safety at all stages of radioactive waste management in Ukraine through optimizing the national transportation and handling infrastructure.

To the extent applicable to the SSE ChNPP as the Recipient, the main tasks of the Project are as follows:

1. Recommendations for optimization and harmonization of the national transportation and handling infrastructure for RAW
2. Detailed designs for RAW standard containers
3. Draft designs of equipment for RAW management and transportation
4. Dissemination of project results and preparation of final report

The following project results were achieved:

The document "Recommendations for optimization and harmonization of the National infrastructure (transportation and technological scheme) for RAW" was developed.

"Technical Designs for standard RAW containers" and "Preliminary designs of the equipment for RAW processing and transportation" were developed. Also the following documents were developed:
- Explanatory Note for Detailed design: “Development of design documentation on container for liquid RAW management”
- Explanatory Note for Draft design: “Development of design documentation on shielded screen for RAW management”
- Explanatory Note for Detailed design: “Development of design documentation on reinforced-concrete container V=1.3 cubic meters in volume for RAW transportation, storage and disposal”
- Explanatory Note for Detailed design: “Development of design documentation on 20-foot steel container for RAW management”
- Explanatory Note for Detailed design: “Development of design documentation on redesigned reinforced-concrete container V=3.0 cubic meters in volume (analogue of KTZ-3.0, KZ-3.0) for RAW transportation, storage and disposal”
- Explanatory Note for Detailed design: “Development of design documentation on redesigned reinforced-concrete container V=2.25 cubic meters in volume for RAW transportation, storage and disposal”
- Explanatory Note for Draft design: “Development of design documentation on auxiliary equipment for RAW management”
- Explanatory Note for Draft design: “Development of design documentation on standard attachment unit to fix a reinforced-concrete container at mechanical transport vehicle”

Project implementation impact:

Ensuring functioning of the infrastructure for solid radioactive waste processing, which is necessary for the Chornobyl NPP decommissioning.