February 21, 2013

Select the another date

Within the framework of the NSC project at the construction site the following activities were implemented:
-        preparation of lifting towers for assembling;
-        assembling of infill elements of main structures;
-        clearance of site and crane rails from snow and ice;
-        Installation of arch metal constructions up to 2-st lifting - according to the design - 4097 tons, installed 103,98 tons (2,54%)

Nearest Events

30 November, 1996 – Unit 1 was finally shutdown
November 30, 1986. It has been signed Deed of the State Commission on acceptance for technical operation of the Shelter object, constructed above the fourth power unit of Chornobyl NPP, destroyed as a result of the accident

News distribution