February 28, 2013

 

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- preparation for assembly of lifting towers
- assembly of the lifting towers
- dismantling of the lifting towers’ sections
- removal of snow and ice from the site and crane runways
- installation of outer cladding purlines
- assembly of Floline 70 steel decking laminates

Assembly of the Arch metal structures (for 2nd lifting)
According to the design - 4,097 tons, 123,98 tons (3%) performed

Assembly of the Arch section outer cladding after 1st lifting
According to the design – 7,847.07m2 area
60.47% performed

Nearest Events

On May, 15, 1976 according to the Preliminary Design requirement and SES the permanent radiation control in areas adjacent to the Chornobyl nuclear power plant was established
On May, 16, 1975 Commission on preparation and commissioning of ChNPP’s Unit 1 was established by Decree of ChNPP Director

News distribution