February 14, 2013

Select the another date

Within the framework of the NSC project at the construction site the following activities were implemented:
-        preparation of lifting towers for assembling;
-        assembling of lifting towers;
-        assembling of infill elements of main structures;
-        clearance of site and crane rails from snow and ice;
-        assembling of external cladding purlines;
-        device of temporary crossover for construction machinery in the east of
excavation pit along axis 34;
-        Installation of arch metal constructions up to 2-st lifting - according to the design - 4097 tons, installed 93,98 tons (2,29%)