On November 27, 2012, a meeting of top management of the Chernobyl Shelter Fund took place with participation of the officials from EBRD, SIP PMU, NOVARKA Consortium, Exclusion Zone Management Agency, and SSE ChNPP.

This day as well, EBRD jointly with SSE ChNPP organized the visit of national and international mass media representatives to ChNPP site to inform world community about progress in New Safe Confinement construction implementation.

On November 24, 2012, the east part of the Arch having 5,300 tonnes of weight was initially raised up to 22 metres on Chernobyl NPP Shelter site. Totally, such lifting will be made three times, and after the last one, the Arch structures will be in their design positions. After this, the east part will be moved towards the Shelter to the holding area, and assembling of the west part will start on released site. Fabricated parts will be put together and slid over the Shelter Object. When fully assembled the New Safe Confinement structure will have a length of 257 metres, a width of 164 metres, a height of 110 metres and a weight of 29,000 tonnes.


Participants of the Chernobyl Shelter Fund top management meeting and mass media representatives visited the Arch assembling area followed by media briefing.

The Head of Exclusion Zone Management Agency Volodymyr Kholosha emphasized the importance of first lifting of the Arch: “The successful implementation of the New Safe Confinement will both significantly reduce the risk of further radiological contamination, and provide equipment and facilities to address the challenges of long term deconstruction of the Shelter Object and its inventory.” He also assured that NSC construction is planned to complete in 2015.

As Director of EBRD Nuclear Safety Department Vince Novak noted during briefing, the site visiting impressed him very much by extent and quality of the work performed. He expressed gratitude to SSE ChNPP General Director Igor Gramotkin, SIP PMU Director Laurin Dodd, the Contractor’s representative and Project (Novarka) Director Nicolas Caille , as well as Ukrainian government authorities for executed work.

“I will inform with pleasure about current progress during Assembly of Contributors meeting to be held in London soon. Total amount of contributors to Chernobyl Programme exceeds forty. We will take the given opportunity and express appreciation to the contributing countries and EBRD shareholders for such weighty contributions they made in Chernobyl problem solving. We all should make every possible effort to complete assigned tasks within established terms and allocated funds for this purpose. I would like to emphasize that I share the optimism of my colleagues, and I am sure that this project can be and will be fully completed.”

To perform the Shelter Implementation Plan, the Chernobyl Shelter Fund will allocate about €1.54 billion. About two-thirds of this amount will be the cost for New Safe Confinement. The EBRD acts as administrator of the Chernobyl Shelter Fund, which was established in December 1997 by the G-7 and other contributing countries to help Ukraine transform the existing Chernobyl sarcophagus into a safe and environmentally stable system. Since 2009 the EBRD is one of the largest contributors to the Chernobyl funds, having pledged €325 million towards implementation of the ChNPP projects.

On the 26th of November the Chernobyl NPP site was visited by Mr. Philippe Dubuisson, a newly appointed Counselor of Ambassador of France on nuclear energy issues in Russia and Ukraine, with accompanying persons.

The objective of the visit, as emphasized by Mr. Dubuisson, is to be familiarized with work progress of the projects, implemented with the participation of French companies and financed at the expense of Chernobyl Shelter Fund and Nuclear Safety Account, in which France is one of the largest contributors.

In the course of the visit the guests met with Mr. Igor Gramotkin, the SSE ChNPP General Director, who told them about the latest achievements at the ChNPP site, in particular, about active works on constructing the New Safe Confinement. They visited the Erection Area for constructing this facility and the town of Prypiat.

On the 26th of November the Chernobyl NPP site was visited by Mr. Philippe Dubuisson, a newly appointed Counselor of Ambassador of France on nuclear energy issues in Russia and Ukraine, with accompanying persons.

The objective of the visit, as emphasized by Mr. Dubuisson, is to be familiarized with work progress of the projects, implemented with the participation of French companies and financed at the expense of Chernobyl Shelter Fund and Nuclear Safety Account, in which France is one of the largest contributors.

In the course of the visit the guests met with Mr. Igor Gramotkin, the SSE ChNPP General Director, who told them about the latest achievements at the ChNPP site, in particular, about active works on constructing the New Safe Confinement. They visited the Erection Area for constructing this facility and the town of Prypiat.

On November 24, 2012, at the Chernobyl NPP Shelter Object site the first lifting of the East part of the Arch with weight of 5,300 t up to height of 22 m was performed. This has become another achievement in constructing the New Safe Confinement. In total, three lifting operations will be performed for the East part of the Arch.

On 23rd of November metal structures of the Arch and the jacking system were completely inspected. The load of 100% was imposed on this system by lifting the Arch for 100 mm. Following that, operability of the jacking system was controlled and geodetic survey of position of the Arch’s metal structures and foundations was carried out.

The lifting operations are performed using 40 strand jacks, placed at 10 lifting towers. Each tower is 45 m high.

A great scope of preparatory works was implemented prior to the first lifting of the Arch. The area was cleaned-up from trees, bushes and construction debris, resulted from dismantling of buildings and structures. More than 57,733 m3of technological materials and solid RAW was removed from the Shelter Object industrial site. The Arch’s foundations, lifting towers and the erection area’s platforms of 57,667 m2 in area were constructed.

 

On November 24, 2012, at the Chernobyl NPP Shelter Object site the first lifting of the East part of the Arch with weight of 5,300 t up to height of 22 m was performed. This has become another achievement in constructing the New Safe Confinement. In total, three lifting operations will be performed for the East part of the Arch.

On 23rd of November metal structures of the Arch and the jacking system were completely inspected. The load of 100% was imposed on this system by lifting the Arch for 100 mm. Following that, operability of the jacking system was controlled and geodetic survey of position of the Arch’s metal structures and foundations was carried out.

The lifting operations are performed using 40 strand jacks, placed at 10 lifting towers. Each tower is 45 m high.

A great scope of preparatory works was implemented prior to the first lifting of the Arch. The area was cleaned-up from trees, bushes and construction debris, resulted from dismantling of buildings and structures. More than 57,733 m3 of technological materials and solid RAW was removed from the Shelter Object industrial site. The Arch’s foundations, lifting towers and the erection area’s platforms of 57,667 m2 in area were constructed.